“… about the relevant principles applicable to the interpretations of covenants in leases or grants of planning permission. In Cherry Tree Investments v Landmain [2012] EWCA Civ 736; [2013] Ch 305 at paragraphs 129 and 130 the principles applicable to the construction of a facility agreement and registered charge were considered. The major…”
“…ublic documents a restrictive approach should be adopted to the use of background information in their interpretation: Cherry TreeInvestments Ltd v LandmainLtd [2012] EWCA Civ 736, [2013] Ch 305.…”
“…ctive interpretation cannot be used to supply a whole clause which the parties have mistakenly forgotten to include: Cherry Tree Investments Ltd v Landmain Ltd [2012] EWCA Civ 736, [2013] Ch 305 at [131] and [144]. As the quotation from Lord Hoffmann demonstrates, a corrective interpretation can only be invoked where something has gone w…”